Wendover Green Tunnel

This will be a 1185 metres (0.73 miles) long ‘cut and cover’ tunnel. The south portal will be adjacent to Bacombe Lane and the north portal alongside Folly Bridge over the A413. Bacombe Lane will be closed and realigned via a temporary link road to Ellesborough Road for one year before being reinstated across the green tunnel. Ellesborough Road will be diverted via a temporary link road to the north for two years before being reinstated along its original alignment. Six residential properties in Ellesborough Road and Wendover Cricket Ground and Pavilion have been demolished. The Wendover Memorial Woodland has been partially destroyed. Three PRoWs are closed and two temporarily diverted during construction. All will be realigned over the tunnel.
Beyond the tunnel the route enters the Wendover north cutting and then leaves the Chilterns crossing under Nash Lee Road. The road will be temporarily diverted over the cutting during construction of the underbridge.

NB. ADT – Articulated dump truck.

Wendover Green Tunnel looking east – Apr. 2021 (22_48)
Wendover Green Tunnel looking east – Apr. 2021 (22_47)
Bacombe Lane looking west across the tunnel portal – Nov. 2024 (22_134)
Looking south from the tunnel portal towards Grove Farm underbridge – Nov. 2024 (22_133)
Looking north along the Wendover green tunnel – Nov. 2024 (22_132)
Bacombe Lane looking east across the tunnel portal – Nov. 2024 (22_131)
Grove Farm Culvert construction alongside Bacombe Lane – Nov. 2024 (22_130)
Construction of the Grove Farm Culvert opening – Nov. 2024 (22_129)
Bacombe Lane temporary link road towards Ellesborough Road – Nov. 2024 (22_128)
Bacombe Lane temporary link road from the junction with Ellesborough Road – Nov. 2024 (22_127)
Looking north towards the tunnel north portal – Feb. 2021 (22_46)
ADT crossing the Ellesborough Road – Aug. 2024 (22_126)
ADT descending the slope under the Ellesborough Road diversion – Aug. 2024 (22_125)
Ellesborough Road diversion looking east over the tunnel cutting – Aug. 2024 (22_124)
Wendover green tunnel cutting looking north – Aug. 2024 (22_123)
Wendover green tunnel looking north towards the north portal – Aug. 2024 (22_122)
Transported spoil removed from previous excavations – Aug. 2024 (22_121)
Diaphragm wall excavation for Wendover north cutting retaining wall – Aug. 2024 (22_120)
Wendover green tunnel from the Ellesborough Road diversion – Aug. 2024 (22_119)
Bacombe Lane and the Wendover green tunnel south portal – Jun. 2024 (22_118)
Looking south from the Wendover green tunnel south portal towards the Small Dean north embankment – Jul. 2024 (22_117)
Temporary Bacombe Lane link road – Jul. 2024 (22_116)
Bacombe Lane link road junction with Ellesborough Road – Jul. 2024 (22_115)
Wendover green tunnel crossing Ellesborough Road – Jun. 2024 (22_114)
Wendover Green tunnel beyond Ellesborough Road – Jun. 2024 (22_113)
Wendover green tunnel looking towards north portal – Jul. 2024 (22_112)
Wendover green tunnel looking towards Wendover north cutting – Jul. 2024 (22_111)
Looking north towards the Wendover north cutting – Jul. 2024 (22_110)
Looking north towards the Wendover north cutting – Jul. 2024 (22_109)
Nash Lee Road overbridge looking east – Jun. 2024 (22_119)
Looking west along Bacombe Lane towards the temporary link road – Apr. 2024 (22_108)
Looking east along Bacombe Lane towards the temporary link road – Apr. 2024 (22_107)
Looking north along the temporary link road towards Ellesborough Road – Apr. 2024 (22_106)
Bacombe Lane temporary link road junction with Ellesborough Road – Apr. 2024 (22_103)
Looking east towards the Wendover green tunnel – Apr. 2024 (22_105)
Looking north along the Wendover green tunnel from the Ellesborough Road diversion bridge – Apr. 2024 (22_104)
Looking south from the tunnel portal across Bacombe Lane – Mar. 2024 (22_102)
Looking north along the tunnel route from Bacombe Lane – Mar. 2024 (22_101)
Bacombe Lane Looking east across the tunnel north portal – Mar. 2024 (22_100)
Bacombe Lane looking east towards the tunnel crossing – Mar. 2024 (22_99)
Looking north from Bacombe Lane towards the north tunnel portal – Mar. 2024 (22_98)
Looking south across Bacombe Lane towards the Small Dean north embankment – Mar. 2024 (22_97)
Looking east across Bacombe Lane temporary link road and the south tunnel portal – Jan. 2024 (22_96)
Ellesborough Road diversion looking east towards Wendover station – Jan. 2024 (22_95)
Wendover green tunnel looking east towards Wendover – Jan. 2024 (22_94)
Wendover green tunnel north portal looking east – Jan. 2024 (22_93)
Nash Lee Road temporary overbridge looking east – Jan. 2024 (22_92)
Bacombe Lane looking north west across the Wendover tunnel portal – Jul. 2023 – (22_91)
Looking south towards Grove Farm underbridge and Small Dean north embankment – Jul. 2023 (22_90)
Bacombe Lane looking east across the Wendover tunnel crossing – Jul. 2023 (22_89)
Bacombe Lane looking east towards Wendover tunnel crossing – Jul. 2023 (22_88)
Small Dean north embankment beyond Grove Farm underbridge – Jun. 2023 (22_87)
Temporary Bacombe Lane link road awaiting construction – Jun. 2023 (22_86)
Ellesborough Road diversion looking east towards Wendover Station – Jun. 2023 (22_85)
Wendover north cutting and concrete batching plant – – Jun. 2023 (22_84)
Nash Lee Road temporary diversion – Jun. 2023 – Jun. 2023 (22_83)
Temporary Nash Lee Road diversion, stopped up road and realigned Nash Lee Lane – Jun. 2023 (22_82)
Temporary bridge taking the Nash Lee Road diversion over the Wendover north cutting – Jun. 2023 (22_81)
Looking east towards the bridge taking the Nash Lee Road diversion over the Wendover north cutting – Jun. 2023 (22_80)
Haul road crossing Nash Lee Road – Jun. 2023 (22_79)
Looking north across the Ellesborough Road diversion towards the Wendover tunnel north portal – Apr. 2023 (22_78)
Looking south from the Bacombe Lane re-alignment (22_77)
Bacombe Lane looking north – Feb. 2023 (22_76)
Bacombe Lane looking west – Feb. 2023 (22_75)
Bacombe Lane looking east towards the tunnel portal – Feb. 2023 (22_74)
Bacombe Lane looking east past the temporary link road – Feb. 2023 (22_73)
Bacombe Lane temporary link road – Feb. 2023 (22_72)
Looking north from Ellesborough Road towards the north tunnel portal – Feb. 2023 (22_71)
Looking north from Ellesborough Road towards the Wendover north cutting – Feb. 2023 (22_70)
Looking south towards Bacombe Lane and the tunnel south portal – Feb. 2023 (22_68)
Wendover Memorial Woodland – Feb. 2023 (22_69)
Looking north along the tunnel route from Ellesborough Road – Feb. 2023 (22_67)
Looking south towards Ellesborough Road – Feb. 2023 (22_66)
Looking north across the Ellesborough Road diversion – Feb. 2023 (22_65)
Looking north across the Ellesborough Road diversion – Feb. 2023 (22_64)
Looking north across the Ellesborough Road diversion – Dec. 2022 (22_63)
Looking northeast across the Ellesborough Road diversion – Dec. 2022 (22_62)
Looking north along the Wendover green tunnel route – Dec. 2022 (22_61)
Bacombe Lane looking across the tunnel portal – Jun. 2022 (22_60)
Looking south along the north cutting towards Small Dean viaduct – Jun. 2022 (22_59)
Bacombe Lane looking north along the tunnel portal – Jun. 2022 (22_58)
Bacombe Lane looking west towards the haul road crossing – Jun. 2022 (22_57)
Looking south along the haul road from Bacombe Lane – Jun. 2022 (22_56)
Looking north along the tunnel route past the cricket pavillion – Jun. 2022 (22_55)
Looking north west towards the tunnel north portal – Jun. 2022 (22_54)
Looking east towards the junction of Nash Lee Road and the A413 Wendover bypass – Jun. 2022 (22_53)
Wendover green tunnel south portal looking east – Apr. 2022 (22_52)
Wendover green tunnel looking east – Apr. 2022 (22_51)
Wendover green tunnel (north) satellite compound – Apr. 2022 (22_50)
Looking north east across B4009 Nash Lee Road – Apr. 2022 (22_49)
Wendover green tunnel looking east – Nov. 2021 (22_45)
Wendover Green Tunnel looking east – Mar. 2019 (22_42)
Wendover Green Tunnel looking east – Apr. 2021 (22_30)
Wendover Green Tunnel looking east (22_29)
Looking north towards the green tunnel north portal – Jun. 2015 (22_24)
Wendover green tunnel (22_17)
Looking north towards the Wendover green tunnel from Grove Farm underbridge – Apr. 2019 (22_16)
Tunnel south portal looking north – Aug. 2010 (22_15)
Bacombe Lane looking west across the tunnel portal- Apr. 2016 (22_14)
Bacombe Lane looking west from the tunnel portal – Apr.2016 (22_13)
Bacombe Lane looking east across the tunnel portal – Feb. 2020 (22_12)
Bacombe Lane looking east – Feb. 2020 (22_11)
Wendover green tunnel south portal looking north – Mar. 2019 (22_10)
Looking south from PRoW-W13a/1 towards the south tunnel portal – Apr. 2011 (22_09)
Looking north towards the green tunnel – Sep. 2019 (22_08)
Looking east towards the green tunnel from PRoW Wen11 – Apr. 2016 (22_07)
PRoW Wen 55/1 looking west across the north tunnel portal – Jun. 2016 (22_06)
Looking east from the tunnel portal – Jun. 2016 (22_04)
PRoW Wen 55/1 looking west from the north tunnel portal – Jun. 2016 (22_03)
Looking south from the tunnel portal – Jun. 2020 (22_02)
Looking north from the tunnel portal – Jun. 2020 (22_01)